HS2's two Euston tunnel boring machines are halfway through their 4.5-mile drive, between West Hampstead and Kilburn High Road. They reach Euston in 2027.
The two machines boring HS2’s tunnel to Euston have passed the halfway mark. HS2 Ltd announced it on 23 November.
By 17 November both machines were between West Hampstead and Kilburn High Road stations, HS2 said. They have bored 2.25 miles of a 4.5-mile drive from Old Oak Common into central London.
Overview
- What: HS2’s Euston tunnel, the fifth and last of the line’s deep bored tunnels, is half built.
- Where the machines are: between West Hampstead and Kilburn High Road stations, as of 17 November.
- Next: the machines finish their drive in 2027, underground on the approach to Euston.
- Trains: not yet. A report submitted to Camden Council this autumn says HS2, including Euston, is expected to open between 2040 and 2043.
The two machines
The tunnel boring machines are called Karen and Madeleine. Each weighs 1,624 tonnes. They set off from HS2’s station site at Old Oak Common in January and March 2026.
HS2 gave these figures for the drive:
- a rate of about 16 metres a day
- work around the clock, seven days a week
- 1.5 million tonnes of excavated material expected over the whole programme
- 48,294 concrete segments to line the tunnel, made in Hartlepool
The machines are run by the Skanska Costain STRABAG joint venture, HS2’s London tunnels contractor. Its delivery lead, Eddie Edmonds, said the work was taking place “up to 50 metres beneath London”.

What happens at Euston
The machines will stop underground on the approach to Euston in 2027. HS2 said the main parts of each machine will then be pulled back out through the tunnel.
The cutting head, 8.53 metres across, will be dug out of what HS2 calls the Euston Cavern. The outer shell at the front of each machine will stay in the ground for good, grouted in behind the tunnel lining.
Above ground, HS2’s contractor has begun the bulk excavation of the new station site. Most of that spoil is leaving Euston by train rather than lorry. HS2 said on 17 November that this would take more than 10,000 lorry trips off the roads around Euston and across London.
What they said
Rail Minister Lord Hendy said: “This achievement marks another important step in delivering HS2 into the heart of London.”
HS2 Ltd chief executive Mark Wild called it “a magnificent achievement”. He said the company was “in the last phases of a root and branch full-programme reset that will safely deliver the railway at lowest reasonable cost”.
HS2’s release gives no new date for the first trains into Euston. The developers’ scoping report for the land over the station, dated October 2026, says that on the latest government announcements HS2 including Euston will open between 2040 and 2043. We reported on that plan for up to 1,500 homes over Euston earlier this month.
What it means for you
- No trains for years. Euston’s HS2 platforms are expected in the early 2040s. Nothing changes for passengers at Euston now.
- The tunnelling is deep. HS2’s contractor says the machines are working up to 50 metres below ground.
- Euston’s building site continues. Freight trains will take a further 135,000 tonnes of spoil from the station site over the next ten months, HS2 said.