The University of London wants two more storeys on its Gower Street halls, 128 extra rooms and a walkway to Malet Street. Councillors decide on 19 November.

Two University of London halls of residence on Gower Street could gain 128 rooms and a public walkway through to Malet Street. Camden’s Planning Committee will decide the plans for Bonham Carter House and Warwickshire House on Thursday 19 November.

Council planning officers recommend approval, according to their report to the committee. Two local amenity groups and at least three households object, mainly to the extra height.

Overview

  • What: two-storey roof extensions across both buildings, taking the halls from 365 rooms to 493.
  • The walkway: a new route through the ground floor of Bonham Carter House, from the end of Chenies Street to Malet Street.
  • Who: the University of London, which owns and runs the halls. The application is 2025/5802/P.
  • When: Planning Committee, Thursday 19 November 2026, 7pm.
  • Recommendation: grant permission, subject to a legal agreement.

What is planned

The site sits on the western edge of the university’s Bloomsbury campus, at 52 to 60 Gower Street. Warwickshire House, to the north, is eight storeys and built in an art deco style. Bonham Carter House, to the south, is six storeys and Edwardian. Both have entrances on Gower Street and back onto Malet Street.

The plans include:

  • taking off the top floor of Bonham Carter House and the top two floors of Warwickshire House
  • a replacement floor plus two new floors on Bonham Carter House, and two new, larger floors on Warwickshire House
  • 128 more student rooms, 493 in all, of which 27 would be accessible rooms
  • a public route through the ground floor of Bonham Carter House between Gower Street and Malet Street
  • two small commercial units, 79 square metres in total, off the new route
  • new lifts and stairs in the courtyard, rooftop plant behind louvres, and landscaping
  • cycle parking up from 48 spaces to 146, with no car parking

The student housing floorspace would grow from 15,035 to 19,055 square metres.

The walkway

The new route would run from the eastern end of Chenies Street, across Gower Street and through Bonham Carter House to Malet Street. Officers say it is a “strategic route” in the council’s Bloomsbury Vision. It would give “a direct line through from Russell Square in the east to Goodge Street in the west” on quieter streets.

The route would slope gently, at 1 in 21, so it is step-free. On Gower Street it would open through a large arch in the front of the building.

The objections

The Bloomsbury Conservation Area Advisory Committee objects. It says the buildings are already much taller than the Georgian terraces opposite. The extra storeys could make them taller than anything else on Malet Street north of Keppel Street, it says.

The Charlotte Street Association also objects to the height. It worries the walkway would send large groups of students along Chenies Street into the quieter streets of Fitzrovia, with noise in the evenings.

Neighbours’ objections raise the skyline, views of Senate House, nearby listed buildings and noise from building work.

Officers accept the scheme causes a “low degree of harm” to the Bloomsbury Conservation Area and several nearby Grade II listed buildings. They say the extra student housing and the new route outweigh it. On the walkway, they say the claim of crowds and noise is “simply not evidenced”, and that students’ behaviour would be managed through a student management plan.

Rents

The university already lets the rooms “at significantly lower rates than other PBSA operators”, the report says, referring to purpose-built student accommodation. Rather than set a share at the London Plan’s affordable rate, the legal agreement would keep all the rooms below market rent.

What the university would pay

The legal agreement attached to the permission would include:

Item Amount
Public open space £148,845.60
Pedestrian, cycling and environmental improvements £128,000
Carbon offset £60,135
Construction management plan support £35,000
Construction impact bond £35,000
Highway works £30,000
Review of the CA-E controlled parking zone £25,000
Electric vehicle charging £20,000
Travel plan £11,348
Cycle and e-scooter hire £10,000
Disabled parking space nearby £4,000

The scheme would also offer 31 apprenticeships and four work placements during construction, according to the report.

What it means for you

If you live around Gower Street, Malet Street or Chenies Street, the main changes would be the taller roofline and the new route through the block. Building work would run under a construction management plan, which the university would have to agree with the council before starting.

The committee meets at 7pm on Thursday 19 November. The agenda and reports are on the council’s meeting page.

Sources